|
Wall-To-Wall Progress
Lifts $105 Million SR-414 Project Toward Early Completion
(1st / 2nd Quarters 2008)
|
 |
|
Ranger Construction has made
“wall-to-wall” progress on a 2.7-mile elevated extension of
SR-414/Maitland Rd. in Orange County, Fla., part of the John Land Apopka
Expressway project. Ranger provided reinforced earth (RE) wall
construction along with its complete range of excavation, grading, pipe
and paving services. Shown in this view are the Keene Rd. entrance/exit
ramps and bridge. (Photo by Leo Nelson) |
| |
|
 |
|
Ranger’s SR-414 project included
construction of 23 RE walls, some extending up to 60 feet high, such as
this section along the entrance ramp from Hiawassee Road.
(Photo by Leo Nelson) |
| |
|
 |
|
The attractive finished look of
the RE wall (also referred to as mechanically stabilized earth (MSE) wall
on this project) is shown near the Gas Line Bridge on Ranger’s SR-414
project.
(Photo by Leo Nelson) |
| |
|
 |
|
A closer view of the SR-414
bridge over Keene Rd. shows a long stretch of retaining wall to the far
side of the bridge. (Photo by Leo
Nelson) |
|
 |
|
Scott
Fowler and Engineers Misty Bayer and Lisa Jones discuss
progress on Ranger North’s SR-414 project in Orange
County, Fla. (Photo by Carl
Thiemann) |
| |
|
 |
|
Hoe
Operator Louis Bryant loads an articulated haul truck
driven by Nick Grice. Up to 60 off-road haul trucks —
along with as many as 150 on-road dump trucks — were put
into action during the peak days of production.
(Photo by Carl Thiemann) |
| |
|
 |
|
Grader
Operator John Hughes shapes the dirt as it approaches one
of the roadway’s many bridges.
(Photo by Carl Thiemann) |
| |
|
 |
|
Loader
Trainee Margarita Quirno spreads road base material.
(Photo by Carl Thiemann) |
| |
|
 |
|
Ranger
North’s Quality Control team, including John Jones, will
perform more than 12,000 density tests on the project.
(Photo by Carl Thiemann) |
| |
|
 |
|
Ray Rueda
pressure cleans one of 23 mechanically stabilized earth (MSE)
walls on Ranger’s SR-414 project prior to painting, as
George Ignatius works the lift controls.
(Photo by Carl Thiemann) |
| |
|
 |
|
SR-414
Engineer Misty Bayer reviews production quantities with
Superintendent Charlie Geiger, Area Manager Pete Scholer,
Superintendent Walt Pierce and Area Manager Mark Webber.
(Photo by Carl Thiemann) |
| |
|
 |
|
Roller
Operator Mike Richards compacts the dirt to eliminate
excessive voids, or tiny air pockets, ensuring that the
road base has the stability and strength needed to support
traffic. (Photo by Carl Thiemann) |
| |
|
 |
|
Margarita
Quirno guides a truck bearing road rock into dumping
position. |
| |
|
 |
|
Haul truck
driver Nick Grice and Dozer Operator Gerald Hines repeat
the cycle of dumping and spreading to build the roadway up
to its proper height, a process involving more than 3
million cu. yds. of material throughout the entire
project, including embankments.
(Photo by Carl Thiemann) |
| |
|
 |
|
Hoe
Operator Brad Driggers readies another bucket of material
while excavating a retention pond. Though the dirt
contains moisture initially, in dry weather it must be
sprayed with water during grading to achieve proper
compaction. (Photo by Carl Thiemann) |
| |
|
 |
|
To keep
pace with the project’s accelerated schedule, Ranger built
half of the walls itself, a first for the company,
utilizing equipment from its recent Medley, Fla.,
acquisition. Subcontractor Dane Construction performed
the balance of the wall work. (Photo
by Carl Thiemann) |
Keeping road construction projects on schedule is a challenge
in any location. But in Florida during the summer, when its
“Sunshine State” motto packs up and heads out on vacation,
daily downpours can wash away even the most conservative
production estimates.
Ranger’s North Division took full advantage when dry weather
and plenty of available equipment allowed huge production
advances on a $105 million SR-414/ John Land Apopka Expressway
project in Orange County. The 2.7-mile elevated roadway, with
23 sections of reinforced earth wall towering up to 60 ft.
high, was scheduled for completion in mid-2009, but is now
expected to be finished by year-end.
Clear Skies, Ready Fleet
For once, Mother Nature heard Florida’s collective summertime
chant and made the “rain, rain, go away.” Months of
unseasonably dry weather gave earthmoving crews a great
opportunity to get well ahead of schedule. They excavated and
placed as much as 35,000 cu. yds. a day to build up the
elevated roadway and the many reinforced earth walls that
support much of its length.
But to haul 3 million cu. yds. of material you’d need a vast
fleet of trucks – far more than you might expect to round up
in a busy market like Orlando, right?
In other years, that might be the case. But with other major
projects in the area either winding down or not yet bid, there
was an abundance of available haul trucks just waiting to hit
pay dirt.
Ranger put up to 150 dump trucks a day to work – 10 times the
number that might normally be available – to keep pace with
its accelerated earthmoving schedule.
“Any other time during the past 10 years, if I had called and
requested even 30 trucks, I’d be lucky to get half that
amount,” said Project Manager Scott Fowler, who used Star
Hauling to supply the vehicles.
Wells Keep Water Flowing
Even with cooperative weather and plenty of trucks, the road
to production still faced a speed bump along the way — a big,
dusty speed bump. Crews were able to move massive quantities
of earth, but it was all bone-dry. Without at least some
moisture, the material couldn’t be compacted enough to meet
density requirements.
Normally on Florida projects, “fill” dirt dug from retention
ponds or other “borrow” areas has plenty of moisture in it –
sometimes too much, especially during the rainy season,
requiring pumps to extract the excess prior to excavation. But
dry earth must be watered as it is placed, so it can be
compacted enough to support eventual traffic loads.
And while Ranger had permitted and drilled an onsite well to
provide water, it didn’t yield enough for the increased
production rates. Fortunately, Ranger’s well of good luck was
still flowing. In yet another favorable turn in the road,
project engineers discovered two additional wells within the
project boundaries – dug years earlier for agricultural
irrigation – and put them into service, as well.
Combined, the wells kept enough supply on tap so Ranger could
operate up to five water trucks a day during its peak of
production, allowing compaction of the roadway material and
keeping haul road dust to a minimum.
By the time the job is finished, Ranger’s Quality Control team
will have conducted more than 12,000 density tests to ensure
compaction of the road base, subgrade, utilities backfill,
embankments and nearly two dozen sections of reinforced earth
wall supporting the roadway.
Great Teamwork
The SR-414/John Land Apopka Expressway job presented some very
favorable job site conditions and the entire project team
worked hard to make the most of them, Fowler noted, turning
Ranger’s largest project to date into one of its most
successful, as well.
That same sense of teamwork also enabled Ranger North to get
well ahead of schedule on another sizable project, widening a
section of US-27 in Clermont, Fla. Valued at more than $25
million, that contract was completed near the end of 2007,
more than 100 days early.
|